BSES never invited Madhuvan RWA for such meetings. I had been hony.secretary of DOCHBS Ltd for six years. Despite raising issue in bhagidari, no Nodal Officer ever invited for any meeting.
I attended because Mr.Sharma who is contributor had advised me to come.Thanks to Mr. Sharma.
During meeting, point regarding increasing transformer capacity(augmentation of existing transformer by replacing it with higher rating) came up.
I was surprised that BSES wants consumers to tell their loads and then augmentation.
I could not contain myself. I told all that practice in DELHI and throughout india is to record loadings in accordance with prescribed intervals.
AUGMENTATION of transformer capacity and laying of additional feeders had to be started when it is loaded around 75%.
It appears that earlier practice has been abandoned.
MY VERY HUMBLE SUGGESTION TO ALL IS;
1.All such meetings must be minuted and if NOT then we refuse to attend.
2. We share information regarding such meetings so that these are well attended and our grievances ventilated.
3. BSES has committed in writing that breakdowns are attended within stipulated time frame.
4.Kindly list out supply failures due to any reason in your area for more than FOUR HOURS.
5. Through notification, DERC HAS EXTENDED DATE for filing objections for another six days.
Above information will help to expose BOGUS claims.