CAG says that the Delhi Jal Board (DJB), responsible for the territory's water
supply, has added only 1 MGD
(million gallons per day) capacity of sewerage treatment plants, while laying
about 900 km
of sewer line during 2007-12 with an
expenditure of Rs 1,634.18 crore.
“The
DJB had not prepared any perspective plan for sewage management for XIth five
year plan, and could collect and treat
only 367 MGD (54%) out of 680 MGD of sewage generated in Delhi,” the report
said.
Furthermore,
there was a lack of equitable distribution of drinking water within the NCT,
the CAG said, “due to lack of reliable data on population and water supplied to
different areas,” and the absence of comprehensive metering of water meant that
“less than 40% of water produced was
billed during last three years.”
"The
drinking water was not being distributed
equitably amongst the population due to lack of reliable data on population
and water supplied to different areas," it said
HOSPITALS :
In
New Delhi’s hospitals, “emergency
departments were not providing required services due to lack of essential
equipment, medicines and adequate staff,” the report said, adding that “all
the test checked hospitals were lacking in facility for purified and clean
drinking water.”
In
GTB, 31 medicines were not available for
a month last year while in Rao Tula Ram Memorial hospital, patients
complained that they had to purchase medicines from outside.
At Ambedkar hospital, the CAG found that 47 essential drugs were not available on many occasions during a period between 2009 and 2012.
More curiously, the CAG said that the 1000-bed Guru Teg Bahadur Hospital and LN (Lok Nayak) Hospital, “have been using ambulances, mainly for miscellaneous purposes instead of for the patients”, apart from the fact that these vehicles did not have “essential equipment for basic life support system”.
At Ambedkar hospital, the CAG found that 47 essential drugs were not available on many occasions during a period between 2009 and 2012.
More curiously, the CAG said that the 1000-bed Guru Teg Bahadur Hospital and LN (Lok Nayak) Hospital, “have been using ambulances, mainly for miscellaneous purposes instead of for the patients”, apart from the fact that these vehicles did not have “essential equipment for basic life support system”.
"The
OPD services were affected due to shortage
of medical equipment, medicines, injections, infrastructure and medical support
items. The Emergency Departments were not providing required services due
to lack of essential equipment, medicines and adequate staff," it said.
In a glaring shortcomings, it was found that five hospitals did not have blood banks while the license for blood bank was not renewed in GTB hospital.
Underlining issues at the Directorate of Health Services, the CAG reported that no construction work has started at the land sites for 10 hospitals, ranging in capacity between 60-700, that were allocated between 1997 and 2008.
In a glaring shortcomings, it was found that five hospitals did not have blood banks while the license for blood bank was not renewed in GTB hospital.
Underlining issues at the Directorate of Health Services, the CAG reported that no construction work has started at the land sites for 10 hospitals, ranging in capacity between 60-700, that were allocated between 1997 and 2008.
DELHI POLICE :
“Most
of the funds earmarked for
modernisation of Communication Branch of Delhi Police were not utilized,” the CAG said, “and as such, the modernisation
of communication network in Delhi Police was not achieved.”
“Physical implementation of Intelligent Traffic System could not be started as of March 2012 due to deficient planning, thereby, depriving users of benefit of world class traffic system in Delhi,” it added.
“Physical implementation of Intelligent Traffic System could not be started as of March 2012 due to deficient planning, thereby, depriving users of benefit of world class traffic system in Delhi,” it added.
TAX REVENUE :
While
the tax revenues of the state increased by 21% to Rs 3,494 crore, the report
pointed out short payment of value added
tax ( VAT ) amounting over Rs 2,321 crore.
CAG has blamed imprudent decision making of the Delhi government in not getting the insurance cover on the basis of current valuation of assets by Indraprastha Power Generation Company Limited, resulting in a loss of Rs 2.33 crore due to under insurance.
CAG has blamed imprudent decision making of the Delhi government in not getting the insurance cover on the basis of current valuation of assets by Indraprastha Power Generation Company Limited, resulting in a loss of Rs 2.33 crore due to under insurance.
The
non-tax revenue, which constituted 2.06% of total revenue receipts during 2011-12 decreased by 89% to Rs 3,728
crore over previous year, it added.
Besides, the report also mentioned that about 39% of the audited cable operators in the city failed to pay taxes for the past three years. Moreover, the state department of finance was unable to recover entertainment tax Rs 1.26 crore from 12 cinema hall owners and luxury tax amounting to Rs 9.76 crore from the hoteliers.
Besides, the report also mentioned that about 39% of the audited cable operators in the city failed to pay taxes for the past three years. Moreover, the state department of finance was unable to recover entertainment tax Rs 1.26 crore from 12 cinema hall owners and luxury tax amounting to Rs 9.76 crore from the hoteliers.
TRANSPORT :
The
auditor has criticized the department of transport for implementing the cluster
bus scheme, “without a well laid out
plan and concurrence of the Finance Department or Legislature.” The scheme
involved corporatisation of private stage carriage buses.
DELHI TRANSCO :
The
CAG also slammed Delhi Transco Ltd, a Delhi government company in-charge of major power
transmission lines, for not being able
to recover an amount of Rs 754.83 crore as transmission charge from BSES
Rajdhani Power Ltd and BSES Yamuna Power Ltd.
OTHERS :
On
implementation of projects under Jawaharlal Nehru National Urban Renewal
Mission, the auditor said the city Government
could not utilise Rs 196.88 crore out of total grant of Rs 2823.18 crore.
"Construction
of 44,720 Dwelling Units had to be dropped due to non-availability of hindrance
free sites. Only 85 out of completed
10,684 DUs could be allotted to the beneficiaries," it said.
The auditor
said delay in taking decisions by the Government escalated the cost of construction of Signature bridge on river
Yamuna by Rs 672 crore.
more points will be uploaded soon.