Hearing regarding madhuvan 15ft public passage encroached by Universal public school preet vihar

In continuation to hearing held by chairman PGC on 2nd august 2010,
The hearing took place as scheduled today 1/09/2010 in the chamber of chairman pgc.
School principal, mcd officers were present.
From society side, hony secretary sh.op rai, joint secretary sh.b.l.rastogi and my self attended.
The perpetual sublease of houses beyond which school has encroached public passage were shown to chairman and photo copy placed on record.
The school sublease was produced by school principal.
The perusal of school sublease indicated that there is 15ft public passage of madhuvan .
Further, it was also seen that area under possession of school is more than land allotted.
It was also brought out that though school came into existence in 1984, but building completion certificate was only applied in 2007 which was REJECTED by mcd.
This makes the school building illegal construction and functioning without any authority.
It was also pointed out that land was allotted for PRIMARY SCHOOL but now senior secondary school is functioning from 2 acre plot and what exist at site is not what was provided in building sanctioned plans for constructing this building.
Now it is for MCD authorities to act. Since 2005, society has been fighting to get back our public passage so that residents of madhuvan and neighbouring colonies could use it.